Construction Update Resurfacing Rte 100

Construction Update 
Wilmington-Stratton STP PS19(7) 
[Wilmington-Stratton Resurfacing Project] 
 
DATE: Thursday, July 2, 2020  
PROJECT TYPE: Roadway resurfacing project  
LOCATION: Route 100 through the towns of Wilmington, Dover, and Stratton. The project begins in 
Wilmington at the intersection of East Main Street and North Main Street, continuing for 11.605 miles 
through the towns of Dover and Stratton, ending near the Stratton-Wardsboro town line (near Penny 
Avenue). 
TRAFFIC IMPACT: For the week of Monday, July 6 through Friday, July 10, between the hours 7 AM and 5 
PM, motorists can expect alternating one-way traffic along the construction route in Dover and Stratton. 
Flaggers will be present to guide motorists through the work zone.  
SPECIAL CIRCUMSTANCES/NOTICES: This week, construction activities include paving the final wearing 
course along Route 100 in Dover and Stratton, and installing permanent roadway signs in Wilmington, 
Dover and Stratton.  
DURATION: Monday through Friday, 7 AM to 5 PM.  
PROJECT COMPLETION: July 2020 
Contact Information: 
Name – Delia Makhetha 
Phone – 603-851-8561 
Email – delia.makhetha@wsp.com  
 
 
Crews working along Route 100 